September 2001 This
month I mainly did rework on some sections already completed, along
with some detailing. I ran into some issues with the plans not being
correct, along with another model makers Fitzgerald, which also was incorrect
that I was using for reference. In my study of the many photo's of
the Fitzgerald and the wreck footage I found the errors. Nothing better to
work with then photo's, I guess I learned my lesson.
The paint is on it's way !!!
A fine gentlemen that works for Oglebay Norton is supplying it for
me. I met him threw the ISMA that I'm in. That paint really means a lot
to me and it's working out!!!!!!!!!!!!
I
concentrated on the Pilot House mainly, getting it completed other then
the fine detailing. I'm pretty much as far as I can get till I get the
paint.


One
error I found was in the bottom railing being to short. As you can see I
had to lengthen it by 2 inches. The plans are incorrect as you can see
between the print and the photo.